Cavity wall construction
Outer leaf and blockwork inner leaf raised together, with insulation, wall ties, cavity trays and weep vents set as the drawings call for.
Bricklaying & masonry subcontractor · West London
GRDBRICKWORK supplies directly employed bricklaying gangs to main contractors and developers on new-build residential schemes.
Outer leaf and blockwork inner leaf raised together, with insulation, wall ties, cavity trays and weep vents set as the drawings call for.
Fair-faced work to the specified bond and joint profile. Reveals, sills, arches, corbels and soldier courses.
Load-bearing and non-load-bearing internal walls, partitions, piers and retaining structures.
DPC, cavity trays and closers, lintels bedded and openings formed and sealed to the detail.
Boundary and garden walls, copings, paving and the site brickwork that gets left to last.
Cutting out and replacing defective brickwork, repointing, and clearing snagged work ahead of handover.
Bricklaying is done in gangs, not by individuals.
Two bricklayers work either side of a line so an elevation goes up to gauge in one operation. That is how packages get priced, and it is how programme dates get met. A lone bricklayer cannot run a line.
We supply labour, supervision, plant and small tools. Materials are normally supplied by the principal contractor and all work is carried out on your site under a subcontract package.
Our bricklayers are directly employed on PAYE rather than taken on day rate, so the same gang stays on your job from first lift to handover. Every gang works to the drawings and the specification, checks its own line, level, plumb and perpends, and works to the site’s risk assessments and method statements.
Send us the drawings and the programme dates. We will tell you straight whether we can hit them.